Pavi Construction Update: Week of Feb. 16
Plumbing rough-in was almost completed this past week thanks in part to a group of volunteers including Austin Landes (Make It Rain), Ben Leatherman and Jon Studt. Four others helped (Kyle Nyce, Jim Frankenfield, Eric and Frank Sirianni) to make the trip a success. Today (Feb 16) was so cold that very little work was done other than prepping for the close-in of the main entry porch.
If weather is decent, that porch structure may be wrapped up this week. The main job for this week is exterior insulation. This will help protect sheathing, give increased R-value and be our main air barrier in the stick frame part of the building.
Volunteer opportunities for the very near future include window and door setting (skilled), radiant tubing help (un-skilled) and siding staining (un-skilled). Contact Brandon (802-672-5220) to help. Or sign up here.